During Downtime: System Specific Situations

This section describes specific fallback workflows for different systems & services at KKBM when CCMS, PhIS or other critical systems are temporarily inaccessible.


General BCP As Initial Flow​

Staff must first follow the General BCP Activation Process (see below), before proceeding with their own unit respective downtime SOP.

  • The BCP Manager leads this process after consulting with unit coordinators, ICT and Helpdesk.
  • Leaders & Coordinators must fully understand this activation process to manage clinic-wide escalation and BCP declaration.
  • All Staff must know and follow their own unit's fallback SOP to ensure safe service delivery once BCP is active.
Trigger

System disruption detected at any service point — CCMS, PhIS, QMS, network, or power failure.


1

Notify BCP Unit Coordinator 👤

First point of contact within the affected unit

Notification

Unit staff immediately inform their respective Unit BCP Coordinator of the system disruption.

2

Notify BCP Manager 👤

Clinic-wide escalation

Unit BCP Coordinator escalates to the BCP Manager for clinic-level assessment and decision-making.

3

Identify Type of Downtime

Total vs Partial

Assessment

Total Downtime

Path A

All critical systems (CCMS, PhIS, QMS, network) are simultaneously unavailable.

  • Inform Head of Unit
  • BCP Manager announces Downtime Activation clinic-wide

Partial Downtime

Path B

Only specific system(s) are down (e.g., QMS only, or PhIS only). Other systems remain operational.

  • BCP Manager announces Downtime Activation for affected unit(s) only
  • Non-affected units continue normal operations
4

Identify Root Cause

Application vs Infrastructure

Assessment

Application Issue

CCMS/PhIS application crash, login failure, module unresponsive

  • Contact Helpdesk (Muar ICT Helpdesk App / BKD WhatsApp)
  • Proceed with BCP activities while awaiting resolution

Infrastructure Issue

Network failure, power outage, hardware malfunction etc.

  • Contact ICT Focal Person for first-level triage
  • Seek resolution via BKAD / vendor support
  • Activate Unit-Specific Downtime SOP
  • Proceed with BCP activities while awaiting resolution

Flowchart Image Placeholder

Original flowchart image to be inserted here.

Suggested path: /img/bcp/general-bcp-activation-flow.png


Next Steps — Unit-Specific SOPs​

After BCP is activated, proceed to your unit's specific downtime SOP:

Contributor

FJ

Dr Fuad Jaafar

Facilitator, CCMS • KK Bandar Maharani

84 contributions

Feedback

Send feedback

Page info

Reviewed May 2026
Next review May 2027
Dr Tn Mohd Azlan
Dr Fuad Jaafar

Feedback

Send feedback

© CCMS Hub. Content on this site was prepared for internal clinical use. Please request permission before reproducing or republishing on other platforms.